    This 6,687-square foot building was one of MCG’s first construction projects. Construction began in late June of 2011 and was completed in four months. MCG managed the excavation of footers and placement of reinforcing steel, building the concrete footers and foundations, laid the perimeter drainage tile and drainable fill. In addition, we were responsible for all of the placement and compaction of sub-base and concrete slabs, exterior wall framing, roof assembly, exterior trim carpentry, exterior masonry, the installation of doors as well as the storefront entrance and windows. The MCG team self-performed a great deal of the work for this project.